Mhlana Somopho Water Project
Project Date
Commencement Date: 01 March 2021
Contract Period: 12 Months
Contract Completion Date: 31 March 2022
Client
King Cetshwayo District Municipality
Project Description
Mhlana Somopho Phase 3A, Water Tower and Pump Station.
- 7.0 km of 315mmØ PVC-o bulk Gravity main
- 0.9km 160mmØ PVC-o bulk gravity main
- 500kl capacity elevated command steel
- supply and installation of associated valves and specials and chambers
- Construction of new pump station
Contractor
Makheleni Construction
Contract Number
KCDM/MIG/02.2020